    Posted by Saul Stringer on 05/26/2022 at 2:51 AM

    Hello all,

    After a number of calls to Quantum I seem to have found a solution to our scheduling issue using the shop control module.

    I was curious what others use to schedule their work orders in the shop control module (on mass). The forward/backward schedule for works order is simple, but need something a little more robust – which Quantum have set up for us.

    I am sure there are other companies out there that repair and OH landing gear, so was just curious what approach you take, using the shop control module?

    Thanks in advance

    Saul

    John Baxter replied 3 months, 2 weeks ago 2 Members · 1 Reply
  • 1 Reply
  • Shop Control – Scheduling

    John Baxter Latest Reply 3 months, 2 weeks ago 2 Members · 1 Reply
  • John Baxter

    Member
    06/14/2022 at 6:18 AM

    Saul,

    I’d suggest process automation for this which schedules the full BOM structure as well as all the child work orders throughout multi level assemblies like Landing Gears, Engins, APUs, etc. Contact me through LinkedIn and we can discuss